5.15.4.
Pantograph X-axis angel adjustment
The pantograph can be adjust at respect to the slope of the road in sideway direction (X-axis)
between -6.0º to 6.0º in steps of 1.5º, see also section
Maximum slope of the road in X-axis
on Page 34.
1. Remove the M8 bolts (A) on each side of the suspension (4x).
2. Put the bolts (A) in a safe location as it will be installed again later on.
3. Rotate the pantograph to the correct angle position.
4. Install the M8 bolts in the new angle position slots.
5. Tighten M8 bolts (A) (4x).
5.16.
Installation of the cables inside Charge Post
DANGER
Make sure that the main switch of the power supply group for the product
is set to the OFF position. Do a voltage check to make sure that the
electrical power is disconnected from the system. Secure against
resetting.
5.16.1.
Open the door and remove cover plate
Preconditions:
Key that was removed from the Charge Pole.
A minimum of two persons is required.
Tool: torx screwdriver (size 2163TX-T30).