Placement and Connection
5.1. About placement and connection
When the construction phase is finished, the HVC-PD E-Bus Charger can be placed and
connected.
The planning steps for the placement and connection phase are shown in the figure below.
Usually the procedure can be done within one day.
C1
Route the cables
on Page 55.
C2
Unpack
on Page 55.
C3
Move Power Cabinet to position
on Page 57 and
Install Power Cabinet onto the
foundation
on Page 60.
C4
Connect the AC power cable
on Page 66,
Connect the DC power cables
on Page 73,
and
Connect the communication fiber cables
on Page 85.
C5
Unpack the Charge Pole
on Page 87.
C6
Move the Charge pole to position
on Page 88,
Install Charge Pole onto the foundation
on Page 90 and
Pantograph adjustment
on Page 97.
C7
Installation of the cables inside Charge Post
on Page 103.
C8
Install cover plates
on Page 118 and
Grouting of the pole construction
on Page 120.