Electrical installation
■
General requirements
Electrical installation of the safety system must be performed according to the practices
outlined in chapter
Planning the electrical installation
in the drive hardware manual.
Chapter
Installation checklists (page 41)
provides additional advice for the planning.
All wiring must be well protected, routed and clamped where practicable.
When installing cabling it must be assured that there is no pulling or pinching on the cables.
■
Ensuring the EMC compatibility
The system must only be used in the EMC environment it is designed for, or necessary
mitigations must be applied.
34 Planning for installation
Содержание FSPS-21
Страница 1: ... OPTIONS FOR ABB DRIVES FSPS 21 safety functions fieldbus module User s manual ...
Страница 2: ......
Страница 4: ......
Страница 11: ...Further information Table of contents 11 ...
Страница 12: ...12 ...
Страница 26: ...26 ...
Страница 38: ...38 ...
Страница 42: ...42 ...
Страница 46: ...46 ...
Страница 69: ...Configuring safety PLC 1 Select safety telegram to use on slot 2 Leave slot 1 empty PROFINET IO Start up 69 ...
Страница 72: ...Switch or router ABB drive ABB drive ABB drive PLC Safety PLC 72 PROFINET IO Start up ...
Страница 86: ...86 ...
Страница 136: ... Configuring FSPS 21 with TIA14 1 Open TIA and create a new project 2 Select your CPU from the list 136 PROFIsafe ...
Страница 144: ...19 In ABB_Drive FB add blocks DPRD_DAT and DPWR_DAT 20 Insert values to blocks 144 PROFIsafe ...
Страница 147: ...26 In device configuration right click FSPS icon and select Assign device name PROFIsafe 147 ...
Страница 155: ...Select Addresses tab to see the correct IO addresses PROFIsafe 155 ...
Страница 169: ...6 To check the Device number of the FSPS 21 module select the General tab PROFIsafe 169 ...
Страница 178: ... starting the system does not cause any danger 178 Start up ...
Страница 186: ...186 ...
Страница 192: ...192 ...
Страница 200: ...200 ...
Страница 208: ...208 ...
Страница 212: ......