The acceptance test using the start-up checklists described below (see Validation checklists
for start-up) must be performed:
•
at initial start-up of the safety function
•
after any changes related to the safety function (wiring, components, settings, etc.)
•
after any maintenance work related to the safety function.
The acceptance test must include at least these steps:
•
having an acceptance test plan
•
testing all commissioned functions for proper operation
•
testing all used inputs for proper operation
•
testing all used outputs for proper operation
•
documenting all acceptance tests performed
•
testing person signing and archiving the acceptance test report for further reference
■
Acceptance test reports
You must store the signed acceptance test reports in the logbook of the machine. The report
must include, as required by the referred standards:
•
a description of the safety application (including a figure)
•
a description and revisions of safety components that are used in the safety application
•
a list of all safety functions that are used in the safety application
•
a list of all safety related parameters and their values (the drive STO has no safety-related
parameters, but listing the non-safety related parameter
31.22 STO indication run/stop
and its setting is recommended)
•
documentation of start-up activities, references to failure reports and resolution of failures
•
the test results for each safety function, checksums, date of the tests and confirmation
by the test personnel.
You must store any new acceptance test reports performed due to changes or maintenance
in the logbook of the machine.
■
Competence
The acceptance test of the safety function must be carried out by a competent person with
expertise and knowledge of the safety function as well as functional safety, as required by
IEC 61508-1 clause 6. The test procedures and report must be documented and signed by
this person.
■
Tools
You need the Drive composer pro PC tool or a control panel to perform the validation
procedures.
Validation checklists for start-up
■
Validation of the PROFIsafe connection
Follow these steps to validate the PROFIsafe connection:
1.
Make sure that the FSPS-21 module is enabled in drive parameter
50.01
(FBA A enable)
or
50.31
(FBA B enable).
Note:
FBA B applies only to ACS880 drives.
174 Verification and validation
Содержание FSPS-21
Страница 1: ... OPTIONS FOR ABB DRIVES FSPS 21 safety functions fieldbus module User s manual ...
Страница 2: ......
Страница 4: ......
Страница 11: ...Further information Table of contents 11 ...
Страница 12: ...12 ...
Страница 26: ...26 ...
Страница 38: ...38 ...
Страница 42: ...42 ...
Страница 46: ...46 ...
Страница 69: ...Configuring safety PLC 1 Select safety telegram to use on slot 2 Leave slot 1 empty PROFINET IO Start up 69 ...
Страница 72: ...Switch or router ABB drive ABB drive ABB drive PLC Safety PLC 72 PROFINET IO Start up ...
Страница 86: ...86 ...
Страница 136: ... Configuring FSPS 21 with TIA14 1 Open TIA and create a new project 2 Select your CPU from the list 136 PROFIsafe ...
Страница 144: ...19 In ABB_Drive FB add blocks DPRD_DAT and DPWR_DAT 20 Insert values to blocks 144 PROFIsafe ...
Страница 147: ...26 In device configuration right click FSPS icon and select Assign device name PROFIsafe 147 ...
Страница 155: ...Select Addresses tab to see the correct IO addresses PROFIsafe 155 ...
Страница 169: ...6 To check the Device number of the FSPS 21 module select the General tab PROFIsafe 169 ...
Страница 178: ... starting the system does not cause any danger 178 Start up ...
Страница 186: ...186 ...
Страница 192: ...192 ...
Страница 200: ...200 ...
Страница 208: ...208 ...
Страница 212: ......