RQ Series Startup Form
Job Name:____________________________________________
Date:______________
Address:___________________________________________________________________
___________________________________________________________________________
Model Number:_______________________________________________________________
Serial Number:___________________________________________ Tag:______________
Startup Contractor:____________________________________________________________
Contractor Address:___________________________________________________________
______________________________________________________
Phone:____________
Pre Startup Checklist
Installing contractor must verify the following items.
1.
Is there any visible shipping damage?
Yes No
2.
Is the unit level?
Yes No
3.
Are the unit clearances adequate for service and operation?
Yes No
4.
Do all access doors open freely and are the handles operational?
Yes No
5.
Have all electrical connections been tested for tightness?
Yes No
6.
Does the electrical service correspond to the unit nameplate?
Yes No
7.
On 208/230V units, has transformer tap been checked?
Yes No
8.
Has overcurrent protection been installed to match the unit nameplate
requirement?
Yes No
9.
Have all set screws on the fans been tightened?
Yes No
10.
Do all fans rotate freely?
Yes No
11.
Does any field water piping to the unit appear to be correct per design
parameters?
Yes No
12.
Is all copper tubing isolated so that it does not rub?
Yes No
13.
Has outside air rain hood been opened?
Yes No
14.
Have the damper assemblies been inspected?
Yes No
15.
Are air filters installed with proper orientation?
Yes No
16.
Have condensate drain and p-trap been connected?
Yes No
Ambient Temperature
Ambient Dry Bulb Temperature
°
C/°F
Ambient Wet Bulb Temperature
°
C/°F
Содержание RQ NextGen Series
Страница 2: ......
Страница 26: ...26 Figure 3 RQ Cabinet Standard and Power Exhaust Gasket Locations...
Страница 40: ...40 Figure 23 Post Corner Hole Piping Figure 24 Post Back Hole Piping...
Страница 86: ...86 Figure 35 Example 2 6 ton through the Base Gas Piping Note RQ units will only contain one Heat Exchanger...
Страница 88: ...88 Gas Heater Operating Instructions Figure 36 Gas Heater Instructions...
Страница 95: ...95...
Страница 96: ...96...
Страница 105: ...105 Maintenance Log E Coated Coil...
Страница 107: ...107...