Operator’s Manual for Crawler Crane
Assembly
and
Dismantli
ng
5-72
3
2
1
4
Figure 5-64
Assembly of fixed jib
c)
According to actual condition, choose and assemble several 6m fixed jib intermediate
sections (G33). All fixed jib intermediate sections are connected with double tapered pins
(5), secured the pins on both sides with retaining springs (6) as follows:
6
5
G33
G31
G32
Figure 5-65
Assembly of fixed jib
The components used to assemble fixed jib are shown in the figure 5-17.
For reference only.
Operators manual should be consulted and adhered to.
Summary of Contents for ZCC1100
Page 2: ...For reference only Operators manual should be consulted and adhered to...
Page 4: ...For reference only Operators manual should be consulted and adhered to...
Page 6: ...For reference only Operators manual should be consulted and adhered to...
Page 12: ...For reference only Operators manual should be consulted and adhered to...
Page 14: ...For reference only Operators manual should be consulted and adhered to...
Page 22: ...For reference only Operators manual should be consulted and adhered to...
Page 80: ...For reference only Operators manual should be consulted and adhered to...
Page 82: ...For reference only Operators manual should be consulted and adhered to...
Page 140: ...For reference only Operators manual should be consulted and adhered to...
Page 206: ...For reference only Operators manual should be consulted and adhered to...