4.6.3 Fixation of rope end point
The rope end point must be fixed in accordance with the following steps:
Step 1: insert wire rope (1) into rope lock (2)
Step 2: put wire rope (1) around rope thimble (3) and then insert them together into rope lock (2)
again
Step 3: pull wire rope (1) tightly to make it fixed between rope thimble (3) and rope lock (2)
closely
Step 4: Fix wire rope with a rope clamp (4).
CAUTION
(1) Incorrect fixation of rope end point can diminish the performance of rope and
damage the rope.
(2) Fix rope end point in accordance with the method mentioned in the figure 4-61.
(3) The tightening torque of rope clamp for hoisting rope is 450N.m, while the
tightening torque for derricking rope is 230N.m.
(4) The rope clamp must be tightened regularly so as to avoid looseness of rope end
point due to reduction of rope diameter.
1
2
3
4
Step 1
Step 2
Step 3
Step 4
Figure 4-59
Fixation of rope end point
For reference only.
Operators manual should be consulted and adhered to.
Summary of Contents for ZCC1100
Page 2: ...For reference only Operators manual should be consulted and adhered to...
Page 4: ...For reference only Operators manual should be consulted and adhered to...
Page 6: ...For reference only Operators manual should be consulted and adhered to...
Page 12: ...For reference only Operators manual should be consulted and adhered to...
Page 14: ...For reference only Operators manual should be consulted and adhered to...
Page 22: ...For reference only Operators manual should be consulted and adhered to...
Page 80: ...For reference only Operators manual should be consulted and adhered to...
Page 82: ...For reference only Operators manual should be consulted and adhered to...
Page 140: ...For reference only Operators manual should be consulted and adhered to...
Page 206: ...For reference only Operators manual should be consulted and adhered to...