(2) Tracking Machine onto Trailer
NOTICE
If using slides to raise the machine on to the trailer they must be anchored to the body to allow
the machine to be raised or lowered. The length of the slide must be such as to form an angle of
12°-15° with the ground. The ramp must be at least 4 times as long as the lorry loading surface.
The width of the slide must be at least 1.2 times the width of the tracks (480-500 mm).
Please pay careful attention to the choice of slides and their location on the lorry body; make sure
they are properly fixed and that there is no possibility of slipping during loading and unloading.
Ensure that the lorry has its parking brake on and apply wedges to the tyres to avoid any possible
slippage during loading/unloading.
In the winter, warm the engine and hydraulic system up first, before loading/unloading using slides.
When unloading the machine, the operator must always maintain a safe distance from the machine
in order to avoid any involvement should it tip up.
PROCEDURE
1. Observe all safety warnings.
2. Position suitable ramps at the end of the transporter.
Figure 5.7 - Ramps onto Trailer
3. Ensure that the extraction belt is in the transport position.
4. Ensure that all
loose items are carefully stowed and secured if these are to be transported
on the machine.
5. Start the engine.
6. Ensure the engine speed is at idle.
7. Slowly track the machine onto the transporter, Reference: Chapter 7.
8. Stop the engine.
9. Remove ramps from the end of the transporter.
10. Secure the machine using the tie down transport brackets and all loose items to the transporter.
Summary of Contents for Evoquip Bison 120
Page 2: ...EvoQuip 200 Coalisland Road Dungannon Co Tyrone BT71 4DR Telephone 44 0 28 8774 0701...
Page 208: ...Appendix A Operations Manual Bison 120 20 07 2018 Page A 2 Revision 2 0...
Page 219: ...Appendix C Operations Manual Bison 120 20 07 2018 Page C 5 Revision 2 0 c Main Wiring...
Page 220: ...Appendix C Operations Manual Bison 120 20 07 2018 Page C 6 Revision 2 0 d Relay Box...
Page 223: ......