Installation manual of system “bp408” - Commissioning
8.13
Setting up the emergency call device
According to EN 81-28, every lift must be equipped with an emergency call device
at a permanently manned location. After wiring the emergency call device, set up
the emergency call device according to the attached description. The function of
the emergency call system must be verified through test emergency calls.
8.14
Setting up the group connection
If it is a lift group and all lifts are running correctly as individual control systems,
then establish the group connection with the pluggable cross connections. Check
the correct setting of the group parameters and, in case of an activated landing
control, pay attention to incoming hall calls in parallel for all group participants.
Switch off the landing control for all group participants. Hall calls may now no longer
be accepted. Switch on the landing control one by one for only one group
participant at a time and check the function of the hall calls.
8.15
Setting up the remote diagnosis
The remote diagnosis can be done via different networks. If the wiring is done
according to the available circuit diagrams, you can set up the connection.
NOTE!
For trouble-free commissioning of our WinMOS
®
300 software, the specifications
and instructions from the WinMOS
®
300 manual must be complied with.
Please note that you can shut down the lift on site or via remote data transmission
(DFÜ) unintentionally by entering incorrect parameters (e.g. runtime monitoring set
too low). If switching devices for the parallel operation of a modem and an
emergency call device are used on a common telephone connection, these must
be approved by Böhnke + Partner GmbH.
The options provided by WinMOS
®
300 with regard to the lift attendant function do
not relieve the user of the obligation to ensure, for any system on site, that the
safety equipment (e.g. emergency stop and emergency call) is not put out of
operation by any wilful damage.
A software update of the control system or components necessary for the function
of the lift may only be carried out if it is checked on site by qualified personnel.
Summary of Contents for bp408
Page 2: ......
Page 24: ...24 Installation manual of system bp408 Safety instructions...
Page 52: ...52 Installation manual of system bp408 The control system bp408...
Page 58: ...58 Installation manual of system bp408 Installation and assembly...
Page 80: ...80 Installation manual of system bp408 Electrical connection...
Page 118: ...Installation manual of system bp408 Appendix 118 Appendix A Menu navigation bp408...
Page 119: ...119 Installation manual of system bp408 Appendix B Update of the firmware via USB stick...