4.3 SP SLOPE function
▶
SP SLOPE function to make the Set Point ascend or descent gradually overtime.
▶
When changing the Target SP during FIX run operation, NSP (current SP) will be changed from current
PV to Target SP gradually by assigned ramping rate.
▶ SP SLOPE Operation
▶ Operation
→ Fix Operation
▶ Temperature
Change Ratio:
→ 20.0 ℃/Min.
Amount of change to TSP = [SP(TSP) - PV] and Slope = 20.0℃/min.
→ (70.0 - 30.0 )℃ = 40.0℃, it will take 2 min to ramp up to TSP
☞ For 2 minutes, NSP will be changed from 30.0℃ to 70.0℃ at a constant
rate of 20℃/min.
TSP
SP
PV
2 Min.
SP Change
40.0℃
70.0℃
30.0℃
20.0℃