PAGE 19
Feb 28/07
1D13
5-20-00
PIPER AIRCRAFT, INC.
PA-46-350P, MALIBU MIRAGE
MAINTENANCE MANUAL
9.
Check security of injector nozzles after the first 50 hours of engine operation, then at each
subsequent 100 hours of engine operation.
10.
In S/N’s 4636001 thru 4636089 only
, verify compliance with Piper Service Bulletin No. 1000.
11.
In S/N’s 4636001 thru 4636110 only
, verify compliance with of Piper Service Bulletin No. 1021
or installation of Kit No. 766-654.
12.
In S/N’s 4636001 thru 4636153 only
, verify compliance with Piper Service Bulletin No. 1020.
13.
In S/N’s 4636001 thru 4636126 only
, verify compliance with Piper Service Bulletin No. 1014.
14.
In S/N’s 4636001 thru 4636175 only
, verify compliance with of Piper Service Bulletin No. 1027
or installation of Kit No. 766-656.
15. Flexible hose replacement times are in-service times. In-service dates must be determined by
(1) the date the aircraft was licensed, if new or (2) the date entered in the logbook for the
replacement hose placed in service. Do not use the date stamped on the hose, as time may be
included for shelf life, and not in-service use.
16. Examine cables for broken strands by wiping them with a cloth for their entire length. Visually
inspect the cable thoroughly for damage not detected by the cloth. Replace any damage or
frayed cables.
(a)
See Control Cable Inspection, 27-00-00, or the latest edition of FAA AC 43.13-1.
(b)
At fifteen (15) years time-in-service, begin Cable Fittings 100 Hour Special Inspection, 27-00-00.
17.
In S/N’s 4636001 thru 4636011 only
, verify compliance with Piper Service Bulletin No. 990.
18.
In S/N’s 4636001 thru 4636131 only
, verify compliance with Piper Service Bulletin No. 1017.
19.
In S/N’s 4636021 thru 4636190 only
, verify compliance with Piper Service Letter No. 1023.
20.
In S/N’s 4636001 thru 4636198 only
, verify compliance with Piper Service Bulletin No. 1029
and Lycoming Service Bulletin No. 534.
21.
In S/N’s 4636001 thru 4636215 only
, verify compliance with Piper Service Bulletin No. 1034.
22.
In S/N’s 4636001 thru 4636221 only
, in airplanes which have not installed a Lear Romec P/N
RG9080-J4A/M engine driven fuel pump, verify compliance with latest revisions of Piper
Service Bulletin No. 1035, Lycoming Service Bulletin No. 529A, and Crane/Lear Romec
Service Bulletin No. 101SB020. See also FAA AD 98-18-12.
23. In
S/N’s 4636001 thru 4636030 only
, verify compliance with Piper Service Bulletin No. 994 or
Parker Hannifin Service Bulletin No. 7049.
24. In
S/N's 4636001 thru 4636043 only
, verify compliance with Piper Service Bulletin No. 964B or
Cleveland ESB 7029A or Cleveland SB 7047.
25. In
S/N's 4636001 thru 4636013 only
, verify installation of Kit No. 766-613 per Piper Service
26. In
S/N's 4636001 thru 4636088 only
, verify compliance with Piper Service Bulletin No. 999.
27. In
S/N's 4636001 thru 4636093, 4636095, 4636096 and 4636099 only
, verify compliance with
Piper Service Bulletin No. 1001.
28. In
S/N's 4636001 thru 4636284 only
, verify compliance with Piper Service Bulletin No. 1041 or
Airborne Service Letter No. 56.
29. In
S/N's 4636248 thru 4636309 only
, verify compliance with Piper Service Bulletin No. 1046.
30. In
S/N's 4636001 thru 4636313 only
, verify compliance with Piper Service Bulletin No. 1054.
31. In
S/N's 4636001 thru 4636313 only
, verify compliance with Piper Service Bulletin No. 1060.
32. In
S/N's 4636001 thru 4636313 only
, verify compliance with Piper Service Bulletin No. 1062.
33. In
S/N's 4636021 thru 4636313 only
, verify installation of Kit No. 767-305 per Piper Service
Summary of Contents for Malibu Mirage PA-46-350P
Page 181: ...1I3 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 12 SERVICING ...
Page 361: ...2F11 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 22 AUTOFLIGHT ...
Page 393: ...2G19 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 23 COMMUNICATIONS ...
Page 521: ...3C1 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 27 FLIGHT CONTROLS ...
Page 601: ...3F9 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 28 FUEL ...
Page 641: ...3H1 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 29 HYDRAULIC POWER ...
Page 771: ...4C13 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 32 LANDING GEAR ...
Page 855: ...4G5 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 33 LIGHTS ...
Page 919: ...5C1 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 34 NAVIGATION ...
Page 1071: ...6C1 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 35 OXYGEN ...
Page 1085: ...6C15 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 37 VACUUM ...
Page 1137: ...6F1 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 51 STRUCTURES ...
Page 1173: ...6G13 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 52 DOORS ...
Page 1197: ...6H13 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 55 STABILIZERS ...
Page 1227: ...6I19 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 56 WINDOWS ...
Page 1261: ...6K5 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 57 WINGS ...
Page 1327: ...7C1 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 61 PROPELLER ...
Page 1355: ...7D5 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 71 POWER PLANT ...
Page 1403: ...7F5 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 74 IGNITION ...
Page 1497: ...7J3 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 79 OIL ...
Page 1509: ...7J15 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 80 STARTING ...
Page 1527: ...7K9 PIPER AIRCRAFT INC PA 46 350P MALIBU MIRAGE MAINTENANCE MANUAL CHAPTER 81 TURBINES ...