SINGLE MITRE SAW 50
ENG Rev 1
page 51
6.1.R
OUTINE MAINTENANCE
(
DAILY
)
At the end of the daily working cycle perform the following maintenance operations using the
suction pipe given together with the suction system (optional) or use any other suction device.
We suggest to not use frequently the compressed air gun to not push scraps and chip into the
machine.
OBJECT
FREQUENCY
ACTION
Working table
Every day at
the end of the
working cycle
Clean
Motor protection grid
Use compressed air to eliminate
chips
Electric cable
Check integrity: there must be no
abrasions or cuts
Blade
Check integrity and wear
Air treatment unit FRL
Check level of condensation: if
necessary clean the tank using the
drainage valve
Tank of lubrication liquid for blade
Check the liquid level: if necessary
add lubricant
" Alcut Plus " made by PERTICI
INDUSTRIES S.r.l.
Table 8 - Routine maintenance plan
EVERY DAY AT THE END OF WORK
-
lock the main switch of electric power
-
disconnect the pneumatic air power supply
6.2.
E
XTRAORDINARY MAINTENANCE
(
WEEKLY
)
OBJECT
FREQUENCY
ACTION
blade
Once a week
Check integrity and wear
Electric circuit
Check:
cable insulation safety
differential
protection
device
functionality
continuity of protection conductor
(ground)
Block of every mechanical
components
Check status and functionality
Joints subjected to be blocked
Grease and oil
Table 9 - Extraordinary maintenance plan
Summary of Contents for Univer 50
Page 2: ......
Page 58: ...SINGLE MITRE SAW 50 ENG Rev 1 page 56...
Page 59: ...SINGLE MITRE SAW 50 ENG Rev 1 page 57 ANNEX 1 COMMERCIAL COMPONENTS...
Page 60: ...SINGLE MITRE SAW 50 ENG Rev 1 page 58 DRAWING OF COAXIAL UNIT...
Page 63: ...SINGLE MITRE SAW 50 ENG Rev 1 page 61 ANNEX 2 EXPLODED DRAWING OF MECHANICAL PARTS...
Page 64: ...SINGLE MITRE SAW 50 ENG Rev 1 page 62 DRAWINGS AND LISTS ARE TO BE UPDATED...