Commissioning follows hardware installation. The commissioning task
includes all the initial procedures you must use to bring the Ethernet
Routing Switch 8600 online and set up appropriate access for remote
users.
Commissioning tasks
The following work flow shows the sequence of tasks you perform to
commission the Nortel Ethernet Routing Switch 8600. To link to a task, go
to
“Commissioning navigation” (page 32)
.