5 Mounting
Maschinenfabrik Reinhausen GmbH 2020
100
5293079/01 EN
VACUTAP
®
VM-Ex
5.4.3 Performing transformer ratio test before drying
NOTICE
Damage to the on-load tap-changer!
Damage to the on-load tap-changer due to transformer ratio test being in-
correctly performed.
► Do not perform more than 250 tap-change operations on the on-load tap-
changer. If more than 250 tap-change operations are to be performed,
completely fill the oil compartment with insulating fluid and lubricate slid-
ing surfaces of contacts on the selector and selector gear with insulating
fluid.
► Only switch the on-load tap-changer from one operating position to the
next via the upper gear unit. You can use a short tube (diameter 25 mm)
with screwed-in coupling bolt (diameter 12 mm) with a hand wheel or
crank for this, for example. When using a drill, do not exceed a maximum
speed of 250 rpm.
► Always check the operating position reached through the inspection win-
dow in the on-load tap-changer head cover. Never overshoot the end po-
sitions, which are indicated in the connection diagram supplied with the
delivery.
► For multiple-column applications with a shared drive, link all on-load tap-
changer heads to one another using the horizontal drive shaft parts.
When actuating the change-over selector, a higher torque is required.
1. Switch the on-load tap-changer into the desired operating position. The di-
verter switch operation can be heard distinctly.
2.
NOTICE!
An incomplete tap-change operation may damage the on-load
tap-changer. After operating the diverter switch, continue to crank the
drive shaft of the upper gear unit for 2.5 revolutions in the same direction
in order to correctly complete the tap-change operation.
3. Perform the transformer ratio test.
4. Repeat the transformer ratio test in all operating positions.
5. Switch the on-load tap-changer into adjustment position (see the accom-
panying connection diagram for the on-load tap-changer).
After the transformer ratio test, open the kerosene drain plug in the oil com-
partment if the on-load tap-changer is to be dried with kerosene in the trans-
former tank. After drying, the diverter switch insert must be removed, the
kerosene drain plug in the oil compartment closed and the diverter switch
insert refitted.
Summary of Contents for VACUTAP VM-Ex