6 Commissioning
Maschinenfabrik Reinhausen GmbH 2020
181
5293079/01 EN
VACUTAP
®
VM-Ex
2. Fill on-load tap-changer with new insulating fluid using one of the two free
pipe connections of the on-load tap-changer head.
Figure 213: Pipe connections S and R
3. Take an insulating fluid sample from the oil compartment.
4. Record the temperature of the sample immediately after the sample is
taken.
5. Determine the dielectric strength and water content at a sample tempera-
ture of 20°C ± 5°C. The dielectric strength and water content must comply
with the limit values [
Section 8.3, Page 193] specified in the technical
data.
6.3.2 Bleeding on-load tap-changer head and suction pipe
6.3.2.1 Bleeding on-load tap-changer head
1. Open all forward valves and return valves in the pipe system.