I - 4
General Information
PTO Shaft Speed
1000 rpm
PTO Shaft
Tractor-wide angle with free wheel
Machine-free wheel slip clutch
Hitching
Trailer coupling;
Swinging drawbar
(permitted load min. 1200 kg; MultiCut = 1500 kg)
(height of swinging drawbar variable)
Caution!
When making an adjustment the hexagonal
screws must be tightened up to:
see page 59 for torque moments
Support
Support foot, retractable – variable height.
Pick up Drum
Hydraulic lifting
Height adjustment via bar with holes on support wheel.
Tine carrier
5 piece
No. of tine
13 (16) double tines/tine carrier
Lateral Feed
Right and left augers
Crop Feed
Forced entry via feed rake drum
Feed rake drum with 5 conveyor feed rakes, 1 feeder rake
A cutting drum is connected in series with MultiCut.
Baling ram
Stroke length 750 mm
50 / 38,5 ram strokes per minute
The baling ram moves on 4 guide rollers
5 / 7 blades on the ram
2 blades in the bale channel
Adjusting the baling pressure
electronic-hydraulic regulation via an adjustable
pressure relief valve, adjustable from the tractor
Twine box
both sides, 12 rolls of twine for each
Twine
Synthetic fibre, 130–150 m/kg
In case of reaching end of roll and of broken twine
Electric twine control with acoustic
yand optical signal.
Ejecting residual packs
Standard
Mechanism via a twin action control valve,
operated from the tractor.
Roller chute
Double-acting control valve of the tractor operating valve
for chute and remaining bale ejector at the rear right of
the machine
Depositing packs
Two part pack chute (must be folded up during
transport).
Holding brake
Operation by crank located on the left hand rear side of
the baler
Brake Connections on the Tractor
Balers with compressed air actuated brake
Dual line brake system required
Balers with hydraulically actuated brake
Connection for hydraulic brake system required
Max. operating pressure 120 bar
Summary of Contents for Big Pack 127 / MultiCut
Page 10: ...I 6 General Information ...
Page 15: ...II 5 Safety ...
Page 22: ...II 12 Safety ...
Page 46: ...IV 10 Comfort Controls ...
Page 70: ...VI 16 Settings ...
Page 90: ...X 2 ...
Page 92: ...XI 2 Putting into Operation Again ...
Page 114: ...XII 22 Special Equipment ...