APPLICATIONS OF SUPERSTRUCTURES
APPLICATIONS OF SUPERSTRUCTURES
3.2
ELEMENTS MAKING UP THE COUNTER CHASSIS
–
Printed 603.95.789
–
1 Ed. - Base 02/2014
Cross members
A sufficient number of crossbars, possibly to be placed in correspondence with the fastening clamps to the chassis, must brace the
two sections of the counter chassis.
The crossbars may be open section (e.g. C), or closed section where you would want to impart greater stiffness.
In their connection, suitable gusset plates must be used to give adequate resistance to the connection (see the following Figure on
the left). When you want to achieve greater stiffness in the connection, it can be carried out according to the following Figure on
the right.
193868
Figure 5
Stiffening of the counter chassis
For some superstructures (e.g. tipping bodies, concrete mixers, cranes on rear overhang, superstructures with high centre of grav-
ity), the counter chassis should be stiff in the back.
This can be achieved by increasing the scope of stiffness to obtain:
●
boxing the longitudinal sections in the rear area;
●
adopting closed section crossbars (see Figure 6);
●
applying cross diagonals (see Figure 7);
In general the use of boxed longitudinal sections should be avoided in the front part of the counter chassis.
166684
Figure 6
Summary of Contents for NEW DAILY
Page 1: ...NEW DAILY BODYBUILDERS INSTRUCTIONS L I G H T R A N G E ISSUE 2014...
Page 4: ...Printed 603 95 789 Base 02 2014...
Page 6: ...Printed 603 95 789 Base 02 2014...
Page 8: ...Printed 603 95 789 Base 02 2014...
Page 9: ...Printed 603 95 789 Base 02 2014 SECTION 1 GENERAL INFORMATION...
Page 10: ...Printed 603 95 789 Base 02 2014...
Page 12: ...4 NEW DAILY GENERAL INFORMATION GENERAL INFORMATION Printed 603 95 789 1 Ed Base 02 2014...
Page 25: ...Printed 603 95 789 Base 02 2014 SECTION 2 CHASSIS INTERVENTIONS...
Page 26: ...Printed 603 95 789 Base 02 2014...
Page 86: ...62 NEW DAILY CHASSIS INTERVENTIONS CHASSIS INTERVENTIONS Printed 603 95 789 1 Ed Base 02 2014...
Page 87: ...Printed 603 95 789 Base 02 2014 SECTION 3 APPLICATIONS OF SUPERSTRUCTURES...
Page 88: ...Printed 603 95 789 Base 02 2014...
Page 121: ...Printed 603 95 789 Base 02 2014 SECTION 4 POWER TAKE OFFS...
Page 122: ...Printed 603 95 789 Base 02 2014...
Page 124: ...4 NEW DAILY POWER TAKE OFFS POWER TAKE OFFS Printed 603 95 789 1 Ed Base 02 2014...
Page 136: ...16 NEW DAILY POWER TAKE OFFS POWER TAKE OFFS Printed 603 95 789 1 Ed Base 02 2014...
Page 137: ...Printed 603 95 789 Base 02 2014 SECTION 5 ELECTRONIC SUB SYSTEMS...
Page 138: ...Printed 603 95 789 Base 02 2014...
Page 140: ...4 NEW DAILY ELECTRONIC SUB SYSTEMS ELECTRONIC SUB SYSTEMS Printed 603 95 789 1 Ed Base 02 2014...
Page 189: ...Printed 603 95 789 Base 02 2014 SECTION 6 ADBLUE AND SCRT SYSTEM...
Page 190: ...Printed 603 95 789 Base 02 2014...
Page 192: ...4 NEW DAILY ADBLUE AND SCRT SYSTEM ADBLUE AND SCRT SYSTEM Printed 603 95 789 1 Ed Base 02 2014...
Page 201: ...Printed 603 95 789 Base 02 2014 APPENDIX A DAILY PEOPLE CARRIER...
Page 202: ...Printed 603 95 789 Base 02 2014...
Page 204: ...4 NEW DAILY DAILY PEOPLE CARRIER DAILY PEOPLE CARRIER Printed 603 95 789 1 Ed Base 02 2014...
Page 217: ...Printed 603 95 789 Base 02 2014 APPENDIX B DAILY CNG AND CNG WITH RECOVERY MODE...
Page 218: ...Printed 603 95 789 Base 02 2014...
Page 240: ...Printed 603 95 789 Base 02 2014...