nano3G AP Installation Manual
Commission a nano3G AP
N3G_INST_300 v14.0 for N3G_2.85 © ip.access Limited 2012
Page 48
5.6
Commissioning Finished
Commissioning the AP is now finished.
From this point on, the AP must be managed from the NOS Client, via the NOS Server. If
the AP has not been pre-provisioned in the NOS Server, it must be configured before it is
can enter service. See section 3 for information about AP provisioning.
5.6.1
Finished On Site Commissioning
If commissioning has been done on site, return to the site installation procedure in section
6.2.3 or 6.3.5, as appropriate.
5.6.2
Finished Advance Commissioning
If commissioning has been done in advance of sending the AP on site, it is advisable to
ensure that the AP will connect to its serving NOS Server prior to sending the AP on site. To
do this:
1)
Verify that the AP has been pre-provisioned with a Site in the serving NOS Server.
2)
Provide the AP with an appropriate network connection. If the AP has been
commissioned to use IPsec, this means a network connection that will go via the
Security Gateway, which is likely to require connection of the AP to an external
network.
3)
Power up the AP.
4)
Use the NOS Client to verify that the AP has connected to its serving NOS Server.
The Site for the AP and the AP object should have a green tick symbol against its
icon.
5)
After verifying this, re-pack the AP so that it is ready for delivery to its intended site.