Chapter 3 Operation
POWER CON
PCON-CB/LC
106
Judging completion of pressing operation
The operation monitors the torque (current limit value) in percent in “Pressing” of the position
table and turns pressing complete signal PEND ON when the load current satisfies the
condition shown below during pressing. PEND is turned ON at satisfaction of the condition if
the work is not stopped.
(Accumulated time in which current reaches pressing value [%])
– (accumulated time in which current is less than pressing value [%])
≥
255 ms (Parameter No.6)
Current
Time
Pressing [%]
Operation
start
Approach end
Pressing start
200ms
20ms 75ms
295ms
200ms + 75ms – 20ms
≥
255ms
Pressing complete (PEND output)
Contactiong wark
Decrease in current due to
movement of work
Summary of Contents for PCON-CB series
Page 2: ......
Page 4: ...POWER CON PCON CB LC ...
Page 14: ...POWER CON PCON CB LC ...
Page 32: ...POWER CON PCON CB LC 18 ...
Page 84: ...Chapter 2 Wiring POWER CON PCON CB LC 70 ...
Page 174: ...Chapter 4 Field Network POWER CON PCON CB LC 160 7 EtherCAT Type 8 PROFINET IO Type ...
Page 190: ...Chapter 7 Absolute Reset and Absolute Battery POWER CON PCON CB LC 176 ...
Page 226: ...Chapter 8 Parameter POWER CON PCON CB LC 212 ...
Page 330: ...Chapter 10 Appendix POWER CON PCON CB LC 316 ...
Page 334: ......
Page 335: ......