NO TICE
● To ensure that the SmartLogger will deliver scheduling commands to the
connected solar inverters/Smart PCS, you must select the active or reactive
power control mode before adjusting the active or reactive power for a PV
plant.
● If Active power control mode is set to No limit or Reactive power control
mode is set to No output, the SmartLogger does not send scheduling
commands to the connected solar inverters or Smart PCS.
6.7.2 Setting Active Power Control
If the PV plant has requirements of power limitation, the power grid scheduling
personnel should limit the active power or disable all the active power for the PV
plant, that is, to enable the active power derating mode.
Step 1 Choose Monitoring > Inverter/PCS > Running Param. > Power Adjustment. On
the displayed page, check that Remote power schedule is set to Enable.
Step 2 Set the parameters for active power control and click Submit.
Figure 6-71 Active power control
----End
No Limit
Parameter
Description
Active power control
mode
If this parameter is set to Unlimited, the inverter
operates at full load, and the Smart PCS limits the
power based on the energy storage control policy.
SmartLogger3000
User Manual
6 WebUI Operations