Microgrid compatibility, Grid connection state, and Grid Code based on the
site requirements.
–
In microgrid or off-grid scenarios, you are advised to set Microgrid
compatibility to Enable.
–
In grid-tied scenarios, set Grid connection state to On-grid (PQ). In off-
grid scenarios, set Grid connection state to Off-grid (VSG).
Figure 6-19 Searching for devices
NO TE
▪
During the process of Search for Device, do not perform upgrade operations
(such as upgrading through the app, network management system, or
WebUI).
▪
When you click Search for Device, cable connections (DC and AC) will be
checked before device search (not applicable to third-party devices), and
device addresses will be automatically allocated.
▪
After the cable connection check and device search are complete, if a cable
connection alarm is generated, you can click the alarm icon
to view the
corresponding alarm information.
▪
If an alarm is generated when the cable connection check fails, click the
alarm icon
to view the alarm cause and handling suggestions. After the
fault is rectified, check the cable connections again.
▪
After the cable connection check and device search are complete, click
to
view the corresponding topology information.
▪
After a device is added or deleted, you need to click Search for Device again.
Otherwise, the system topology will not update.
3. Connect to power meters.
SmartLogger3000
User Manual
6 WebUI Operations
Issue 10 (2022-08-20)
Copyright © Huawei Technologies Co., Ltd.
89