Installation Manual – BTS3606A Cabinet Installation
Airbridge BTS3606&3606A CDMA Base Station
Chapter 6 Checking Cabinet Installation
Huawei Technologies Proprietary
6-1
Chapter 6 Checking Cabinet Installation
6.1 Check Before Power-on
You need to check the installation of the equipment and cables before powering on the
BTS3606A.
6.1.1 Equipment Installation Check
Table 6-1 lists check items for equipment installation.
Table 6-1
Equipment installation checklist
SN
Check item
1
The rack is placed according to the design drawing.
2
The rack and base are firmly connected. The rack is stable after installation.
3
The horizontal and vertical errors of the cabinet are less than 3 mm (0.12 in.).
4
All the screws are fastened. Check whether there are plain washer and
spring washer for the screws and whether the spring washer is on the plain
washer.
5
The rack components are not loosed or get damaged and the connecting
cables are not damaged or broken.
6
The cabinet is clean and tidy.
7
The surface of the equipment is clean, the external paint is in good condition,
and the labels or marks are correct, clear and tidy.
8
The front door of the cabinet can be closed or opened smoothly.
9
The RF jumpers are placed according to sectors.
10
When leveling the base by adjusting bolts, use washers to enlarge the stress
surface area to avoid distortion of the base.
11
The cover for the hole of the cabinet is installed.
12
There are no cable ties, stubs, desiccant bags on the cabling rack and the
base of the rack. All equipment is clean and tidy.
13
The lifting lugs of the cabinet are intact. If the paint drops, paint them again.
14
The waterproof measures are taken.
15
The board in the front of the cabinet is fastened.
16
AC/DC modules are properly installed. Especially, when the BTS is
configured into S(1/1/1), two of the five configured AC/DC modules must be
installed in the upper subrack and the rest three in the lower subrack.