Chapter 3
Preparing Superdome for Booting
Installing and Verifying the PDCA
51
2. Using a Volt-Ohm meter (VOM), check the following test points to make sure they conform to
the specifications for the PDCA and local electrical specifications:
Table 3-1
4- and 5-Wire Voltage Ranges
4-Wire
5-Wire
L2 to L3: 200-240 V
L1 to N: 200-240 V
L2 to L1: 200-240 V
L2 to N: 200-240 V
L1 to L3: 200-240 V
L3 to N: 200-240 V
N to Ground:
a
a. Neutral to ground voltage can vary from millivolts to
several volts depending on the distance to the
ground/neutral bond at the transformer. Anything
over 3 V should be investigated by a site prep or
power specialists.
Summary of Contents for 9000 Superdome
Page 8: ...Contents 8 ...
Page 9: ...9 Preface ...
Page 21: ...21 IEC 60417 IEC 335 1 ISO 3864 IEC 617 2 International Symbols ...
Page 22: ...22 Figure 9 Superdome Declaration of Conformity Page 1 ...
Page 23: ...23 Figure 10 Superdome Declaration of Conformity Page 2 ...
Page 24: ...24 ...
Page 32: ...Chapter 1 Introduction Installation Warranty 8 ...
Page 130: ...Chapter 4 Verifying and Booting Superdome Enabling iCOD 106 ...
Page 172: ...Appendix A hp Server rx2600 Support Management Station Configuring the SMS 148 ...
Page 184: ...Appendix C Superdome LAN Interconnect Diagram 160 ...
Page 193: ...Appendix F 169 F A180 Support Management Station ...
Page 230: ...Appendix G Connecting Multiple SPU Cabinets Connecting Cables 206 ...
Page 256: ...Appendix H JUST Exploration Tool Error Conditions 232 ...