GREE GMV5 HR HEAT RECOVERY UNITS
100
Step 2: Turn on the valves for the liquid and gas pipes of each module completely. For the modular
unit, the oil-equalizing valve of each module also needs to be turned on.
Step 3: Make the system to run in commissioning mode via the commissioning software or the main
board of the ODU. (For details, see the description on commissioning.)
Step 4: When the commissioning step goes to refrigerant perfusion, turn on the valve of the
refrigerant tank and perfuse the remaining quantity (m`).
Step 5: After all refrigerant is perfused, turn off valve of the refrigerant tank and wait till
commissioning is automatically is completed for the system.
Step 6: Remove the pressure gauge to finish refrigerant perfusion.
Because R410A is a mixture of refrigerant, therefore, it must be charged in a liquid form.
Otherwise, unit will not work stably and effectively.
Do not expose the R410A refrigerant tank to direct sunlight. Otherwise, the internal pressure
may get too high and cause explosion.
Pipeline for the R410A refrigerating system must have relevant valid certificates.
During welding, avoid overheating the pipeline.
System must not filled with refrigerant other than R410A.
Pipe to be vacuumed : gas pipe, water pipe, common pipe
If the refrigerant amount is not exact, it may not operate properly.
If additionally bottled refrigerant amount is over ±10%, condenser burning or insufficient indoor
unit performance may be caused.
Summary of Contents for GC201808-III
Page 87: ...GREE GMV5 HR HEAT RECOVERY UNITS 83 1 External Connection for Individual Units ...
Page 92: ...GREE GMV5 HR HEAT RECOVERY UNITS 88 ...
Page 227: ...GREE GMV5 HR HEAT RECOVERY UNITS 223 Troubleshooting ...
Page 286: ...GREE GMV5 HR HEAT RECOVERY UNITS 282 Troubleshooting ...
Page 362: ...JF00302879 ...