As the testing sequence progresses, the progress bar will advance to reflect the test progress.
Status indicators in the Data Flow map corresponding to the various system components will be
highlighted in the appropriate color to indicate the current test status, as follows:
•
Green:
All recommended tests for these components have been completed and no problems
were identified.
•
Red:
Problems were identified in these components during the performance of the test.
•
Yellow:
The tests executed so far on these components have passed, but not all
recommended tests have been performed.
6.) At any stage, trackball to the
Pause
button and press
Set
, if required.
7.) To resume testing (from the point where you paused), trackball to the
Start
button and press
Set
.
When the DC Offset Verification Test sequence is complete:
-
the
Diagnostic
Test
window displays the Finished message
-
the View Test Log window opens automatically, listing all tests performed and showing details
of which tests passed or failed, as shown in the example in
.
8.) If necessary, use the scroll bars and/or arrows to scroll through the list of Test results.
NOTE:
For this test, there is one report (ADC Offset verification values) which is listed in the Reports
window on the right. By default, this report is displayed in the Reports window below.
9.) Use the scroll arrows at the bottom of the Reports window (see
) to scroll through the
channels and view the corresponding results.
10) When done, trackball to the
Close
button and press
Set
to close the View Report window.
Figure 7-10 View Test Log - DC Offset Verification Test