Modifications reserved
Page 86/103
OPM_LPS_33E_60K_M12_2GB_V010.doc
Operating Manual
LP 33 Series 60-80-100-120 kVA / S2
8.2.3 From Manual Bypass Q2 to normal function VFI
This procedure presupposes that the
load
is powered by all
manual bypass Q2
switch of the
Parallel
System
, and:
•
The
inverter
is switched OFF;
•
The
manual bypas
s switch
Q2
is closed (Pos. I);
•
The output switch
Q1
is open (Pos. 0);
•
The external
battery
fuses are removed;
•
LED Alarm
blinks.
The
synoptic diagram
, on all UPS units, must display the status
“
LOAD SUPPLIED BY MANUAL BYPASS Q2
”
.
1. Insert the external battery fuses on each unit
.
In case of GE battery cabinet: insert the fuses in their place and close fully the cover of fuse-holder by
using correctly the handle.
2.
Close the output switch (Pos. I) on all UPS units.
When the last
Q1
will be closed the output will be from
mains
in parallel from
automatic bypass
and
manual
bypass Q2
of all UPS units.
The
synoptic diagram
, on all UPS units, must display the status
“
LOAD SUPPLIED BY AUTOMATIC BYPASS AND MANUAL BYPASS
Q2
”
.
`
Home\Commands
COMMANDS
RESET TOTAL OFF
REQUEST TOTAL OFF
3.
Only in case it has been previously activated, restore the
command
“Total Off”
on any one of the units
by entering
the screen:
COMMANDS/
RESET TOTAL OFF
V
`
Home\Meter
BOOSTER
f :
50.0
Hz
L1 :
397
V
L2 :
395
V
L3 :
393
V
Vp :
400
V
Vn :
400
V
4.
Open the manual bypass switch Q2 (Pos. 0) on all UPS units.
The
load
is supplied by the mains through the
automatic bypass
.
Verify on all UPS units, selecting the screen
METERING/BOOSTER/
Vp
and
Vn
, that the booster voltage has reached about
400 Vdc
.
5. Insert the inverter by pressing
“
Inverter ON
”
( I ) key on first UPS unit
.
In case of sufficient output power, the output will transfer to
Inverter
.
LED Alarm
turn Off and the
LED Operation
must be is lit.
The
synoptic diagram
, on first UPS unit, must display the status
“
LOAD SUPPLIED BY INVERTER
”
.
6. Insert the inverter by pressing
“
Inverter ON
”
( I ) key on all other UPS units
.
Do not start the next
inverter
until the sequence of the previous one ends.
As soon as the output power of the
inverters
is sufficient to supply the
load
, the output of the units with
running
inverter
will transfer to
inverter
.
LED Alarm
turn Off and the
LED Operation
must be lit.
The
synoptic diagram
, on all UPS units, must display the status
“
LOAD SUPPLIED BY INVERTER
”
.
END OF PROCEDURE