SECTION 8
8-15
TROUBLESHOOTING-TELESCOPIC SYSTEM
PACKING REFUSE-CONTINUED
HYDRAULIC SEQUENCE
While the carrier and packer panels are moving up,
compacting refuse against the pushout panel, pressure
is building in the case end of the carrier cylinders. This
pressure is also building in a pilot line from the carrier
valve section to the FCV (Front Control Valve) pushout
section. When this pressure reaches 1800 PSI (124
BAR), a relief (resistance) cartridge opens in the FCV
(Front Control Valve) pushout section, allowing some
case end pressure from the telescopic pushout cylin-
der to return to tank. This allows the pushout panel to
come forward slightly.
MAIN CONTROL
VALVE
HYDRAULIC
FLUID TANK
PUMP
FRONT
CONTROL VALVE
TELESCOPIC
CYLINDER
TAILGATE LIFT
CYLINDER
CARRIER
CYLINDER
PACKER
CYLINDER
CARRIER
CYLINDER
TAILGATE LIFT
CYLINDER
P.O. CHECK
VALVE
○
○
○○○○
○
○
○ ○
○
○
○
○ ○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○○○○○
○○○○○○○○○
○
○
○
○
○○○○○
○○○○
○
○
○
○
○
PRESSURE
○ ○ ○ ○
RETURN
TRAPPED OIL
○○○○○
○
○
○
○
○
○
○
○○○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○○
○
○ ○
○ ○
○ ○
○○○○○○○○○○○○○○○○○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○
○ ○○○
Summary of Contents for LEACH 2R-III
Page 2: ......
Page 8: ......
Page 26: ...SECTION 2 2 8 ...
Page 28: ...OPERATION SECTION 3 LOCATION OF OPERATING CONTROLS 3 2 4 6 5 7 8 1 2 3 8 9 10 11 12 7 ...
Page 46: ...SECTION 3 3 20 ...
Page 54: ...SECTION 4 4 8 ...
Page 60: ...SECTION 6 6 4 PREVENTIVE MAINTENANCE 1 2 3 4 5 6 7 8 ...
Page 62: ...SECTION 6 6 6 ...
Page 76: ...SECTION 7 7 10 ...