Tapping a pilot hole
Figure 4-11:
4.9.4
Surface preparation: epoxy mount
Note
The mounting location must provide a flat surface, 1 in. in diameter. If this is not possible, an
alternative mounting procedure must be used. Do not proceed; contact the project manager.
Epoxy mount
1.
If the equipment surface has a radius of curvature that is less than 4 in., grind a flat
surface approximately 1/2 in. diameter.
2.
Using the wire brush and plant-approved cleaner, clean and degrease the surface
area.
3.
Using a 2-part epoxy (such as Emerson P/N A92016), spray the activator onto the
mounting surface.
4.
Place a light coat of epoxy on the surface of the mounting pad (such as Emerson P/N
A212) and hold firmly against the machine spot face surface for 1 minute.
If the adhesive does not set within 1 minute, it is an indication that too much epoxy
is applied or that the mounting surface is not prepared properly. Repeat steps 2
through 4.
Hardware configuration: overview
38
MHM-97453, Rev 1
Summary of Contents for Machinery Health Expert CSI 2600
Page 1: ...User Guide MHM 97453 Rev 1 April 2014 CSI 2600 Machinery Health Expert User Guide ...
Page 8: ...CSI 2600 back view Figure 2 2 Introduction to the CSI 2600 4 MHM 97453 Rev 1 ...
Page 12: ...Introduction to the CSI 2600 8 MHM 97453 Rev 1 ...
Page 26: ...Getting started 22 MHM 97453 Rev 1 ...
Page 64: ...Software configuration 60 MHM 97453 Rev 1 ...
Page 96: ...Data types 92 MHM 97453 Rev 1 ...
Page 100: ...D 2 Internal wiring diagram for the CSI 2600 ...
Page 106: ...Troubleshooting 102 MHM 97453 Rev 1 ...
Page 109: ...Index MHM 97453 Rev 1 105 ...