77
Operation and Installation Manual for SOLIVIA 2.0/2.5/3.0/3.3/3.6/5.0 EU G4 TR
12. Diagnostics and Troubleshooting
EN
12.5 Current Grid Settings
Menu
131 View Grid Setup
Description
The current grid settings can be displayed using
131 View Grid
Setup
The contents of this menu are write-protected.
Accessing the Menu
Main Menu > Install Settings > Grid Selection > View Grid
Setup
➔
Options
Install settings
-------------------
SOLIVIA ##
1. In the main menu, press the
buttons to select
Install
Settings
and then press the
button.
➔
Display settings
Date and time
Language: English
Grid selection
RS485
100 Install settings
2. Press the
buttons to
select
Grid Selection
and then
press the button.
➔
Grid change
View grid setup
-------------------
130 Grid selection
3. Press the
buttons to
select
View Grid Setup
and
then press the button.
→ Depending on the current
grid settings, different
messages may be dis-
played first.
##.#W/##.#kVA
been limited to
of that inverter has
The maximum power
activated
Power balancing is
4. When the messages are dis-
played, press the button to
confirm each.
Fnom: 50.00Hz
Grid: DE LVD
--------------------
131 View grid setup
5. You can view the whole list by
pressing the
buttons.
12.6 Autotest for Italy
Menu
610 IT Autotest
Description
nOTE
The "Italy Autotest" is only available when the
grid has been set to
IT BT 21 < 6 kW
.
In accordance with the CEI 0-21:2012-06 standard, an autotest is
required for PV systems equal to or less than 6 kW.
The autotest is performed during commissioning when the grid is
set to
IT. BT 21 < 6kW
. The autotest can then be performed at any
time.
The Autotest checks the proper operation of the grid and system
protection.
The solar inverter may only be put into operation when the test
result of the last autotest is
Pass
. The reports for the last five
autotests are saved.
During the autotest, all parameters required in CEI 0-21 on the AC
side of the solar inverter are tested.
Once the autotest is complete, the result is displayed (see
Table
12.3, p. 78
). The overall result is "Pass" only when all subtests
have been passed.
Performing Autotest
Main Menu > Diagnostic&Alarm > IT Autotest > Perform
Autotest
➔
USB features
Options
Production info
Diagnostic&Alarm
Inverter info
SOLIVIA ##
1. In the main menu, press
the
buttons to select
Diagnostic&Alarm
and then
press the button.
➔
AT Report 1
Perform autotest
-------------------
610 IT Autotest
2. Select
Perform Autotest
using
the
buttons, then press
the button to perform the
autotest.
→ The autotest starts.
...test ongoing...
611 Perform autotest
3. The Autotest checks the proper
operation of the grid and sys-
tem protection.
→ The test result is displayed
after the autotest is com-
pleted.
IT-Grid: 00.01.00
12.08.2012 09:23:35
Result: Pass
612 AT Report 1
4. You can view the whole list by
pressing the
buttons.