8. Commissioning
Operation and Installation Manual for SOLIVIA 2.0/2.5/3.0/3.3/3.6/5.0 EU G4 TR
40
➔
Time: 14:26:51
Date: 25.05.2012
-------------------
Date and time
18. To change the value, press the button and then set
the value using the
buttons. Press the button to
apply the value.
➔
continue
Time: 14:26:51
Date: 25.05.2012
-------------------
-------------------
Date and time
19. Press the
buttons to select
continue
and then
press the button.
→ The
RS485
menu is displayed.
➔
Baudrate: 19200
ID: 1
-------------------
RS485
20. To change the value, press the button and then set
the value using the
buttons. Press the button to
apply the value.
nOTE
: If multiple solar inverters are
to be connected via RS485, select a
different ID for each inverter. The ID
is also used when saving and loading
settings in order to identify the solar
inverter.
Available IDs:
1 - 254
Available baudrates:
2400 | 4800 | 9600 | 19200 | 38400
➔
continue
Baudrate: 19200
ID: 1
-------------------
-------------------
RS485
21. Press the
buttons to select
continue
and then
press the button.
→ The completion screen will be displayed.
to reselect
ESC:
to confirm
ENTER:
22. Press the button to complete commissioning.
or
Press the button to change settings.
þ
Commissioning is now finished.
nOTE
► If the solar inverter is configured to the
DE
LVD
oder
DK LVD
grids, you can also con-
figure active and reactive power control, see
“10.9 Active Power Control”, p. 56.
► The solar inverter offers some optional
functions available for all grids, see
“10 Set-
tings”, p. 52.
► When done with commissioning, save
the settings (see
“11.4 Saving Settings”,
p. 65
) and swap data (see
“11.6 Saving
Swap Data”, p. 67
) to a USB drive in
order to be able to use them later.