Shipping Damage Instructions
If shipping damage to the SteamCraft V is discovered or suspected,
observe the following guidelines in preparing a shipping damage claim.
• Write down a description of the damage or the reason for suspecting
damage as soon as it is discovered. This will help in filling out the claim
forms later.
• As soon as damage is discovered or suspected, notify the carrier that
delivered the shipment.
• Arrange for the carrier's representative to examine the damage.
• Fill out all appropriate claims forms and have the examining carrier sign
and date each form.
Parts shipped unassembled (figure2-8) can be assembled before or after
the SteamCraft V is connected to the electric power, water supply, and
drain lines. If these parts are to be stored during the connection proce-
dures, place them back i
n
their shipping box place the box back inside the
steamer, and dose the steamer door. Otherwise, assemble these parts
according to the following instructions.
Install The Steam Generator Cover
1. Refer to figure 2-10, and hold the steam generator cover with the short
handle to the left and the long handle to the right. The printing on the top
(of the cover should be right side up (Descale With Kit P/N 101751 -
Remove Daily To Clean).
2. Keeping the cover level, place the right leg of the cover against the
right side of the steam generator body
and the left leg against the
protective baffle on the left side.
3. Lower the cover into place over the steam generator opening.
Install The Fan Guard
1. Refer to figure 2-11 and hold the fan guard so the hanger pin slots are
pointing up and towards the back of the guard.
2. Slide the right side of the guard past the hanger pins, and into the right
rear comer of the steamer compartment.
3. Swing the left side of the guard past the hanger pins, and into the left
rear corner of the steamer compartment. The guard will cover the fan.
4. Holding both sides of the guard, lift it to aline the hanger slots with the
large hanger pins at the back of the steamer.
5. Pull the fan guard forward and down to slide the hanger slots over the
hanger pins.
Printed 4/90
Summary of Contents for SteamCraft V
Page 56: ...Page 54 CET 16 Service Manual Figure 5 1 Block Diagram Printed 4 90...
Page 59: ...CET 16 Service Manual Page 57 Figure 5 2 Control Board Printed Circuit Board Printed 4 90...
Page 73: ...Page 72 CET 16 Service Manual Figure 6 1 MAJOR COMPONENT GROUPS...
Page 80: ...CET 16 Service Manual Page 79 Figure 6 6 ELECTRICAL COMPONENTS ASSEMBLY Printed 4 90...
Page 82: ...CET 16 Service Manual Page 81 Figure 6 7 FAN ASSEMBLY Printed 4 90...
Page 84: ...CET 16 Service Manual Page 83 Figure 6 8 CONDENSER AND DRAINAGE SYSTEMS Printed 4 90...
Page 86: ...CET 16 Service Manual Page 85 Figure 6 9 STEAM GENERATOR ASSEMBLY Printed 4 90...
Page 88: ...CET 16 Service Manual Page 87 Figure 6 10A DOUBLE WATER INLET ARRANGEMENT Printed 4 90...
Page 90: ...CET 16 Service Manual Page 89 Figure 6 10B SINGLE WATER INLET ARRANGEMENT Printed 4 90...