Chapter 21 DLPs A400 to A499
DLP-A442 Verify Pass-Through Circuits
DLP-A442 Verify Pass-Through Circuits
Step 1
In the CTC Circuits window, choose a circuit that passes through the node that will be removed and click
Edit
.
Step 2
In the Edit Circuits window, check
Show Detailed Map
.
Step 3
Verify that the STS and VT mapping on the node’s east and west ports are the same. For example, if the
circuit mapping on the west port is s5/p1/S1 (Slot 5, Port 1, STS 1), verify that the mapping is STS 1 on
the east port. If the circuit displays different STSs and/or VTs on the east and west ports, record the name
of the circuit.
shows a circuit passing through a node (doc-124) on the same STS (STS 2).
Figure 21-2
Verifying Pass-Through STSs
Step 4
Repeat Steps
to
for each circuit in the Circuits tab.
Step 5
Delete and recreate each circuit recorded in Step
. To delete the circuit, see the
. To create the circuit, see
Chapter 6, “Create Circuits and VT Tunnels.”
Step 6
Return to your originating procedure (NTP).
Purpose
This task verifies that circuits passing through a node enter and exit the
node on the same STS and/or VT.
Tools/Equipment
None
Prerequisite Procedures
DLP-A60 Log into CTC, page 17-66
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Provisioning or higher
Summary of Contents for ONS 15454 Series
Page 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Page 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Page 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Page 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Page 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...