53-1004106-15 Installation Guide
Brocade
®
X6-4 Director Hardware Installation Guide
Cable Management Fingers
Cable management fingers install on the equipment rack for cable management.
The Brocade X6-4 Director comes equipped with two vertical cable management finger assemblies. The director can
continue to operate during the replacement of the cable management fingers. Due to the horizontal orientation of the
blades in the device, the finger assemblies are attached to the uprights of the mounting rack.
Time and Items Required for Removal and Replacement
The replacement procedure for the cable management fingers takes less than 5 minutes. A No. 1 Phillips screwdriver is
required.
Removing the Cable Management Finger Assembly
Cable management finger assemblies are shown installed in the following figure.
Figure 71: Cable Management Fingers Installed on Rack Uprights on an X6-4 Director
1. Cable management finger assemblies
Complete the following steps to remove the cable management finger assemblies from rack uprights.
1. Remove the cables from the cable management finger assembly and rearrange the cables around the assembly.
2. Unscrew and save the three (3) screws that hold the finger assembly to the rack upright.
3. Remove the cable management finger assembly.
4. If necessary, repeat steps 1 through 3 for the other finger assembly.
Installing the Cable Management Finger Assembly
Complete the following steps to install the cable management finger assembly:
1. Position and tighten the three (3) screws to secure the vertical cable management finger assembly to the rack upright.
Cable management finger assemblies are shown installed in the following figure.