3.1.7 Cable and Fuse Configuration
Cable designs must be compatible to current and voltage values stated herein, additionally local
instructions must be obeyed about these topics
UPS
RATİNG
(KVA)
RATED CURRENTS (A)
INPUT CURRENTS@MAX
CHARGE CURRENT (3P+N)
OUTPUT CURRENTS @100%
LOAD (3P+N)
380V
400V
415V
380V
400V
415V
10
22
20,9
20,2
19,7
18,8
18
15
33
31,4
30,2
29,6
28,2
27,1
20
44
41,8
40,2
30,3
28,2
27,8
30
66
62,7
60,5
45,6
43,4
41,9
40
89
84,6
81,6
78,9
75
72,4
60
133
126,4
121,7
118,4
112,5
108,5
80
177
168,2
162,1
157,8
149,9
144,5
100
222
210,9
203,3
197,3
187,4
180,7
120
266
252,7
243,6
236,7
224,9
216,7
It should be noted that with non-linear loads, neutral current may rise up to 1.5 times the phase
current.
Ground cable must be connected directly to ground line and must be kept as short as possible.
Typical ground cable cross sections are (for IST5 PF: 1):
4 mm2 for 10KVA
6 mm2 for 15KVA
10 mm2 for 20KVA
16 mm2 for 30KVA
25mm2 for 40KVA
35 mm2 for 60KVA
50 mm2 for 80KVA
70 mm2 for 100KVA
95 mm2 for 120KVA ratings.
The length of the cable must not be over 5 meters.
Summary of Contents for IST5 Series
Page 2: ...2 2 SERVICE MANUAL 10 15 20 30 40 60 80 100 120 160 200 300 KVA...
Page 6: ...9 9 2 PRODUCT DESCRIPTION 2 1 General View 10 15 20 30 40KVA...
Page 7: ...10 10 60 80KVA...
Page 8: ...11 11 100 120 160 200 300 KVA...
Page 13: ...16 16 2 5 Side Interior View 10 15 20 30 40KVA...
Page 16: ...19 19 2 7 Electrical Connections...
Page 35: ...38 38...
Page 36: ...39 39...
Page 51: ...54 54 30 40KVA 60 80 100 120 160 200 300 KVA...
Page 54: ...57 57...
Page 71: ...74 74 1 Turn CB2 ON 10 15 20KVA 30 40KVA...
Page 72: ...75 75 60 80 100 120KVA 2 Stop the UPS using the user front panel Main menu Control Stop...
Page 73: ...76 76 3 Turn CB1 CB3 and CB4 OFF 10 15 20KVA 30 40KVA...
Page 100: ...103 103 Signal Flow Diagram zole trafo means isolated transformer...
Page 102: ...105 105 20 30KVA IGBT Driver 40KVA IGBT Driver...