Fig. 48 Corner of the platform
6
Measure the distance between doors and
safety frame, it is to be 10-12 mm between the
platform corner and the door frame.
Fig. 49 Fixing of doors into pit floor
7
Fixate the door frame into the pit floor.
8
Alt 1
: Fix the door in the floor in two places
through the threshold. See 4
Alt 2
: Fasten two angle brackets in the floor
and fix the door in the angle bracket. See chap-
ter 4
Fig. 50 Outer corner of the platform
9
In this stage, only tighten the fixing at the end
of the door (outer corner of the platform, see
pos 1).
10
Fix the door temporarily during installation with
a side cladding panel in top of the door.
11
Adjust the bottom position of the door with
310 mm and tighten the fixation in the inner
corner.
Note:
Make sure not to cover the
holes in the doors that are
needed for the door cables
and door wires, when fixing
the doors to the architrave.
7000 100 en-GB AD
61
Summary of Contents for 7000
Page 1: ...Vector Installation Manual HQ ...
Page 23: ...ASSEMBLY 5 ASSEMBLY 5 1 FIXINGS 7000 100 en GB AD 19 ...
Page 25: ...ASSEMBLY Fig 15 Mast preparation before installation 7000 100 en GB AD 21 ...
Page 27: ...ASSEMBLY Lift the top section 7000 100 en GB AD 23 ...
Page 33: ...ASSEMBLY 7000 100 en GB AD 29 ...
Page 34: ...ASSEMBLY 30 7000 100 en GB AD ...
Page 42: ...ASSEMBLY The mast shall stand upright the tolerance is Max 2 mm m 38 7000 100 en GB AD ...
Page 70: ...ASSEMBLY Fig 59 Mounting of Filled wall panels 66 7000 100 en GB AD ...
Page 72: ...ASSEMBLY Fig 61 Principal drawing Shaft corners 68 7000 100 en GB AD ...
Page 100: ...This page is intentionally left blank 96 7000 100 en GB AD ...
Page 117: ...OPTIONS Fig 126 Electrical connections external door opener 7000 100 en GB AD 113 ...
Page 140: ...This page is intentionally left blank 136 7000 100 en GB AD ...
Page 142: ...This page is intentionally left blank 138 7000 100 en GB AD ...