11 PREVENTIVE AND CORRECTIVE MAINTENANCE
3BHS206977 E01 REV H
ACS1000I AIR-COOLED
USER MANUAL
164/174
11.6.5
Checking the release conditions for the grounding switch
1.
Check that the auxiliary voltage is switched on.
□
2.
Check that the main power supply is disconnected from
the drive.
□
a) Check that the MCB is open.
When the MCB is open, secure it against closing.
□
b) Check that the feedback signal "MCB is open" arrives at the drive, ie, if the
following indicators are lit:
- LED of digital input DI08 of I/O module -A5201 (-A2)
□
- MAIN SUPPLY ON pushbutton -S5152 (-S2)
When the LED and the pushbutton are lit, the feedback signal "MCB is
open" has arrived at the drive.
□
- If the pushbutton is not lit:
- Check if the 24 V blade-type fuse (X27_P2:14) is blown.
The fuse protects the control circuit of the pushbutton.
□
- If the LED is not lit:
- Check the control-signal wiring between switchgear and drive as
per applicable wiring diagram.
□
3.
Checking the discharge level of the DC link.
- Check if the value of parameter 2.06 DC VOLTAGE is below 50 V.
When the value is below 50 V, the DC link is regarded as discharged. For
information on reading actual values on the CDP control panel, see “10.3.2
Actual signals mode” on page 130.
□
4.
Check the GROUNDING SWITCH UNLOCKED lamp and the
wiring of the lamp.
a) Check if the CDP control panel displays a fault.
A fault prevents the lamp GROUNDING SWITCH UNLOCKED from lighting.
- If a fault is present, follow the instructions in “11.3.4 Standard
troubleshooting procedure” on page 155, before you reset a fault.
- If a fault cannot be rectified and reset, contact the ABB
service organization.
□
Summary of Contents for ACS1000i air-cooled
Page 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000i air cooled User manual ...
Page 3: ...Contents ACS1000i air cooled User manual ...
Page 5: ... 01 About this manual 01 5 16 ...
Page 16: ......
Page 17: ... 02 Important safety information 02 17 28 ...
Page 28: ......
Page 29: ... 03 Power electronics and cabinet features03 29 56 ...
Page 57: ... 04 Control system 04 57 70 ...
Page 71: ... 05 Transportation storage and disposal05 71 78 ...
Page 78: ......
Page 79: ... 06 Mechanical installation 06 79 88 ...
Page 88: ......
Page 89: ... 07 Electrical installation07 89 104 ...
Page 105: ... 08 Commissioning 08 105 110 ...
Page 110: ......
Page 111: ... 09 Operation 09 111 124 ...
Page 125: ... 10 CDP control panel 10 125 148 ...
Page 149: ... 11 Preventive and corrective maintenance 11 149 172 ...
Page 173: ......