![YASKAWA VIPA System SLIO Скачать руководство пользователя страница 221](http://html.mh-extra.com/html/yaskawa/vipa-system-slio/vipa-system-slio_manual_907132221.webp)
9.6 Fast introduction
At the first commissioning respectively after an overall reset with PowerON again of the
CPU, the Ethernet PG/OP channel has no IP address. This can only be reached by its
MAC address. By means of the MAC address, which is printed at the front as
‘MAC PG/
OP:...’
, you can assign IP address data. The assignment takes place directly via the
hardware configuration of the Siemens SIMATIC Manager.
For the configuration of the Ethernet PG/OP channel for productive connections please
follow the following approach:
n
Hardware configuration - CPU
n
Hardware configuration - Ethernet PG/OP channel
n
Configure connections
–
Siemens S7 connections
(Configuration via Siemens NetPro, communication via VIPA handling blocks)
–
Open communication
(Configuration and communication happens by standard handling blocks)
n
Transfer of the complete project to CPU
9.7 Hardware-Konfiguration
At the first commissioning respectively after an overall reset with PowerON again of the
CPU, the Ethernet PG/OP channel has no IP address. This can only be reached by its
MAC address. By means of the MAC address, which is printed at the front as
‘MAC PG/
OP:...’
, you can assign IP address data. The assignment takes place directly via the
hardware configuration of the Siemens SIMATIC Manager.
n
CPU
Chap. 4.5 ‘Hardware configuration - CPU’ page 69
n
Ethernet PG/OP channel
Chap. 4.7 ‘Hardware configuration - Ethernet PG/OP channel’ page 72
9.8 Configure Siemens S7 connections
The project engineering of connections i.e. the "link-up" between stations happens in
NetPro from Siemens. NetPro is a graphical user interface for the link-up of stations. A
communication connection enables the program controlled communication between two
participants at the Industrial Ethernet. The communication partners may here be part of
the same project or - at multi projects - separated within related part projects. Communi-
cation connections to partners outside of a project are configured via the object "In
unknown project" or via deputy objects like "Other stations" or Siemens "SIMATIC S5 Sta-
tion". The communication is controlled by the user program with VIPA handling blocks. To
use this blocks, configured communication connections are always necessary in the
active station.
‘Projecting connections’ page 224
‘Siemens S7 connection - Communication functions’ page 226
The following properties are characterizing a communication connection:
n
One station always executes an active connection establishment.
n
Bi-directional data transfer (Send and receive on one connection)
Overview
Steps of configuration
Overview
Overview
Properties communication
connection
VIPA System SLIO
Deployment PG/OP communication - productive
Configure Siemens S7 connections
HB300 | CPU | 013-CCF0R00 | en | 19-30
221