XO FLOW – Installation instructions
22
5.2.6
Checking clearance between base and floor
During adjustment, it may occur that the unit base or the supporting leg is pressed firmly against the
floor, or alternatively that there is a gap between the rubber sealing and the floor of more than 10
mm.
In either case, the unit base and supporting leg must be re-adjusted using all five adjustment nuts
(see Figure 18).
Note that one turn of an adjustment nut equals a vertical distance of 1,5 mm.
5.2.7
Installation of the unit on an installation plate
If the unit cannot be mounted directly on the floor, an installation plate for installing the unit is
available (XO-492).
Note that installation with steel plate is not allowed if the unit is delivered with X-Ray
adaptor.
Figure 23 – Installation plate and necessary parts
1.
Assemble the four bolts – (1) in Figure 23 – to the four bushings – (4) in Figure 10.
2.
If installed on a wooden floor, place the installation plate on the floor and secure it to the floor
with five 6 x 60 mm screws – (3) in Figure 23
3.
With the special wrench (MG-416), adjust the brass adjustment bushing – (5) in Figure 18 – in
the supporting leg and allow for approximately 5 mm clearance between the supporting leg and
the steel plate surface.
4.
Fit the long rod, washer and nut – (2), (5) and (4) in Figure 23 – in the hole through the
adjustment bushing – (5) in Figure 18 – do not tighten.
5.
Fit the four long rods – (5) in Figure 10 – through the holes in the unit base into the bushings.
6.
Fit the washers and nuts – (12) and (11) in Figure 10 – onto the long rods; do not tighten.
7.
Turn the adjustment nuts – (1) – (4) in Figure 18 – in the unit base, allowing for approximately
5 mm clearance all the way between the unit base and the steel plate surface, and make sure
that all four adjustment nuts rest on the bushings in the steel plate. The nuts on top of the long
rods should be loose.
8.
Place a spirit level on top of the bridge arm post in the longitudinal direction – (A) in Figure 18 –
see Figure 19.
9.
Turn the adjustment nut – (2) in Figure 18 – until the post is plumb in the longitudinal direction
and then tighten the nut on top of the long rod.
10.
Turn the spirit level to adjust the unit stand in the crosswise direction – (B) in Figure 18 – see
Figure 20.
11.
Turn the adjustment nut – (4) in Figure 18 – counter-clockwise and make sure it does not
contact the bushing in the floor.
12.
Turn the adjustment nut – (3) in Figure 18 – until the bridge arm post is horizontal in the
crosswise direction and tighten the nut on top of the long rod.
Содержание FLOW
Страница 1: ...XO FLOW INSTALLATION INSTRUCTIONS...
Страница 2: ...2...
Страница 5: ...XO FLOW Installation instructions 5 10 One month follow up 71 11 Fuses 72 12 Symbols 72...
Страница 17: ...XO FLOW Installation instructions 17 Figure 15 Lifting the unit stand Figure 16 Adjusting the unit base...
Страница 35: ...XO FLOW Installation instructions 35 Figure 43 Fitting of lower outer cylinder...
Страница 38: ...XO FLOW Installation instructions 38 Figure 48 Positioning of the cables Figure 49 Securing the cables...
Страница 44: ...XO FLOW Installation instructions 44 Figure 58 Fitting the brake Figure 59 Fitting the cover plug...