Figure 27: Two Pipe Oil Lines
C
.
TWO PIPE OIL LINES
1. For two piped systems, where more lift is required,
the two-stage fuel unit is recommended.
Table 3 (two-stage) and Table 4 (single-stage) show
allowable lift and lengths of 3/8 inch and 1/2 inch
OD tubing for both suction and return lines. Refer
to Figure 27.
Lift "H"
(See Fig. 25)
Maximum Length of Tubing
"H" + "R" (See Figure 27)
3/8" OD
Tubing (3 GPH)
1/2" OD
Tubing (3 GPH)
0'
93'
100'
2'
85'
100'
4'
77'
100'
6'
69'
100'
8'
60'
100'
10'
52'
100'
12'
44'
100'
14'
36'
100'
16'
27'
100'
18'
---
76'
Lift "H"
(See Fig. 25)
Maximum Length of Tubing
"H" + "R" (See Figure 27)
3/8" OD
Tubing (3 GPH)
1/2" OD
Tubing (3 GPH)
0'
84'
100'
1'
78'
100'
2'
73'
100'
3'
68'
100'
4'
63'
100'
5'
57'
100'
6'
52'
100'
7'
47'
100'
8'
42'
100'
9'
36'
100'
10'
31'
100'
11'
26'
100'
12'
21'
83'
13'
---
62'
14'
---
41'
SECTION X: OIL PIPING (continued)
Содержание V8H SERIES
Страница 76: ...76 Bare Boiler Assembly Continued SECTION XVI Repair Parts continued ...
Страница 78: ...78 Jacket Assembly SECTION XVI Repair Parts continued ...
Страница 80: ...80 V8H3 Thru V8H9 Steam Boilers Trim and Controls SECTION XVI Repair Parts continued ...
Страница 82: ...82 V8H3 Thru V8H9 Water Boilers Trim and Controls SECTION XVI Repair Parts continued ...
Страница 84: ...84 Beckett AFG Burner SECTION XVI Repair Parts continued ...
Страница 94: ...94 SERVICE RECORD DATE SERVICE PERFORMED ...
Страница 95: ...95 SERVICE RECORD DATE SERVICE PERFORMED ...
Страница 96: ...96 U S Boiler Company Inc P O Box 3020 Lancaster PA 17604 1 888 432 8887 www usboiler net ...