Section 1 Page 45
TA3/01/50/01_Iss1Rev3
Rev.No.Jan17/Rev3
1.5.5
Cantilever Brackets
Prior to the commencement of any scaffolding operations, please refer to Sections
1.4.1
General Safety Notes
and
1.5 Assembly Procedures
.
(i) Inside Boards
1. Base out structure according to base
out procedure in Section
1.5.1 Tied Wall
Scaffold Fully Boarded
steps 1 to 11.
Note
Ensure that the entire base is level and
square before proceeding with first lift height.
2. Place appropriate-sized Decks,
Bracing Guardrails, Horizontals and
Cantilever Brackets to complete first
lift safely. Ensure that ladder access
unit is situated in one of the bays to
allow access to next lift.
3. Add additional and appropriate-sized
Standards on top of the existing outer
Standards (as necessary) to allow
placing of the next lift of scaffolding.
4. Repeat placement of appropriate-
sized Decks, Bracing Guardrails,
Horizontals and ladder access unit to
complete the second lift.
SECTION 1.5 Assembly Procedures