1. Base out structure according to base
out procedure in Section
1.5.1 Tied Wall
Scaffold Fully Boarded
steps 1 to 11.
2. Fit temporary Bracing Guardrails to
protect the scaffold run platforms when
working from them. Bracing Guardrails
should be used to create the link between
the scaffold runs.
Note
Ensure that the entire base is level and
square before proceeding with first lift height. It
may be advantageous to fit temporary Bracing
Guardrails to determine the positioning of second
structure and to assist in levelling overall structure.
To assemble top lift only birdcage scaffolds, remove Decks
from the bays that do not require a working platform below
the top lift (leaving ladder access bay in place).
Add Bracing Guardrails between outer and inner Standards
to provide protection to the ladder access bay prior to
removing Decks. Remove Decks from the remaining bays
(from below). Fit Toeboards.
3. Place appropriate-sized Decks, Bracing
Guardrails, and Horizontals to complete
first (ladder access unit) lift safely.
4. Fit Toeboards to each working lift.
SECTION 1.5 Assembly Procedures