22. Select appropriate Decks and deck out
transoms (from below) until the lift is
complete (ensuring that locks on each
end of each Deck are in the locked
position).
Note
Place ladder access unit in one of
the bays to allow access to next lift.
23. Utilising ladder access unit, access can
be gained to Deck level and fix Toeboards
in place.
Note
Ensure that trapdoor is closed when
working on platform.
24. Add additional and appropriate Standards
on top of inner and outer Standards (if
required).
25. Place next lift Guardrails temporarily in
cups immediately above existing deck
Guardrails and engage Wedge.
26. Using GuardAid
®
Positional Tool, raise
temporary Guardrails (step 24) into
position to suit next lift platform and fix in
position and engage Wedge.
SECTION 1.4 Safety Information