SECTION 1.5 Assembly Procedures
(iii) Mobile
Prior to the commencement of any scaffolding operations, please refer to Sections
1.4.1
General Safety Notes
and
1.5 Assembly Procedures
.
The following drawings show the base out procedure for a mobile tower. On completion of
the base out, proceed using steps 2 - 6 on Page 34.
1. Position four Castor
Wheel Jacks and
four Horizontals to
approximate starting
position of first bay.
2. Ensure wheels are
locked, then place first
Standard on Jack and
connect Horizontal in
lowest cup.
4. Place third Standard on
Jack and connect third
Horizontal in lowest cup.
3. Place second Standard
on Jack and connect
second Horizontal in
lowest cup.
5. Continue until all Horizontals are connected. Check
levels along Horizontals and check that bay is square.
Note
Please refer to the
Inspection & Maintenance Guidance Notes for Mobile Structures
on Page 37 when moving Turner OCTO
®
scaffold structures.