12. Place appropriate-sized Decks,
Bracing Guardrails and all
Horizontals to complete first lift
safely. Ensure that ladder access
unit is situated in one of the bays to
allow access to next lift.
Note
Ensure that the entire base is level
and square before proceeding with first
lift height.
13. Add additional and appropriate-sized
Standards on top of the existing
outer Standards (as necessary)
to allow placing of the next lift of
scaffolding.
14. Repeat placement of appropriate-
sized Decks, Bracing Guardrails,
Horizontals and ladder access unit to
complete the second lift.