Turner OCTO
®
Assembly Guide
©Turner Access Ltd 65 Craigton Road, Glasgow, G51 3EQ, Scotland
Section 1 Page 18
TA3/01/50/01_Iss1Rev3
Rev.No.Jan17/Rev3
12. Place next lift Guardrails temporarily in cups
immediately above existing base Guardrails.
13. Using GuardAid
®
Positional Tool, raise
temporary Guardrails (placed at step 12)
into position to suit next lift platform and fix
in position.
14. Continue to raise Guardrails from temporary
location into appropriate position to suit first
lift platform using GuardAid
®
until entire next
lift Guardrails are affixed.
SECTION 1.4 Safety Information