Turner OCTO
®
Assembly Guide
T: +44 (0) 141 309 5555 F: +44 (0) 141 309 5436 www.turner-octo.com
Section 1 Page 33
TA3/01/50/01_Iss1Rev3
Rev.No.Jan17/Rev3
Option 4: Fly By Return
Two runs of scaffolding that meet at a corner but cannot form one of the returns as shown
previously. Therefore, it is necessary to let one scaffold “fly by” the other to maintain scaffold
run platform width. It will be necessary to close the gap with handrailing and Toeboards to
protect users.
In all cases, ensure that Bracing Guardrails are fitted on inside faces of the scaffold
structure if the gap between the building and the scaffold structure exceeds 225mm (or local
regulations, if different).
SECTION 1.5 Assembly Procedures