Refrigeration Maintenance
10-7
To add refrigerant:
1. Connect and purge/evacuate a gauge manifold set to a refrigerant bottle and the suction service valve.
2. Set the refrigerant bottle for liquid charging.
Note: For Category B unit, close all doors on unit and ensure all unit panels and skins are securely attached.
3. Operate the unit in high speed COOL (and the remote evaporators in COOL).
4. Open the valve on the refrigerant bottle and read the suction pressure on the gauge manifold.
5. Add liquid refrigerant through the suction service valve. Open the gauge manifold low pressure hand valve only enough to
permit suction pressure to increase 1.40 bar, 25 psi. This will meter liquid refrigerant slowly into the low side.
NOTE: For Category B unit, after the first additional 0.25kg is added, all doors should be closed and high speed cool should
be maintained. Proceed as per step 7. Wait 5 minutes. Check refrigerant level by opening doors momentarily.
NOTE: Maintain a discharge pressure of 19.00 bar, 275 psi or more.
6. Add refrigerant until the ball 1/4 to 1/3 of the sight glass (bottom sight glass on two sight glass receiver tank). Allow the level
to stabilise (1 to 2 minutes).
• If the refrigerant level is now high, remove refrigerant (see above).
• If the refrigerant level is still low, repeat steps 4 through 6.
• If the refrigerant level is ok, perform a complete refrigerant level check and repeat the overcharge test.
Note: Please take note of your refrigerant type (label on outside of unit), and make sure not to cross-contaminate.
7. Always recover remaining refrigerant from the hoses before disconnecting the gauge manifold set from the unit.
Moisture Indicating Sight Glass (where fitted)
The receiver tank is equipped with a moisture indicating sight glass. The outer edge of the sight glass has a coloured ring
approximately 2.5 mm thick. The colour of the ring indicates the general moisture content of the refrigerant. However, the colour
indication may not be completely reliable.
A system has to operate for at least 15 minutes to change the colour of an indicator ring after the moisture content of the system
has been changed. For example, evacuating a system to remove the moisture will not change the colour of the indicator ring until
the system has been recharged and then operated for at least 15 minutes.
Moisture Indicating Sight Glass
1.
Floating Ball
2.
Coloured Ring
Ring Colour
Moisture Content Indication
Green
Dry
Chartreuse
Caution
Yellow
Wet
Содержание SLXi Spectrum
Страница 17: ...Safety Precautions 2 5 Warning Decals...
Страница 18: ...Safety Precautions 2 6 Warning Decals Information Decals...
Страница 74: ...Unit Description 5 30...
Страница 128: ...Controller Operation 7 28...
Страница 156: ...Electrical Maintenance 8 28...
Страница 177: ...Engine Maintenance 9 21 Integral Fuel Solenoid Components 1 Integral Fuel Solenoid 2 O ring 3 Fuel Injection Pump Groove...
Страница 234: ...Refrigeration Maintenance 10 22...
Страница 309: ...13 Mechanical Diagnosis TK 482 TK 486 and TK 486V Engines 13 2...
Страница 316: ...Mechanical Diagnosis 13 8...
Страница 322: ...Refrigeration System Diagnosis 14 6...
Страница 332: ...Single Temperature Refrigeration System Diagrams 15 10...
Страница 339: ...Multi Temperature Refrigeration System Diagrams 16 7...
Страница 340: ...Multi Temperature Refrigeration System Diagrams 16 8...
Страница 342: ...Wiring Diagrams and Wiring Schematics 17 2...