SMARTZONE UPS INSTALLATION MANUAL
78
Figure 94: Remove Battery Baffle on the EBP
d. Refer to the handling instruction, remove all four battery cartridges. Battery
cartridges are connectorized to a backplane in this EBP unit, there is some
resistance when removing the cartridges (see figure below).
Note:
The Battery
Cartridge is heavy.
Figure 95: Remove Battery Cartridges from EBP
e. Refer to the handling instruction, slide the new battery cartridges into the EBP
unit, battery cartridges are connectorized to a backplane in the unit, there will
be some resistance when inserting the cartridges.
f. Reinstall the battery baffle the screws (reverse order of above steps).
g. Replace the EBP faceplate.
h. Turn the breaker on the back of the EBP unit to the ON position.
3. After all, EBP battery cartridges in the system have been replaced and are connected
to the system.
4. Change the UPS in the system back to the Normal state.
5. Allow time for the UPS to transitions to the Normal state (about 30 seconds).
6.
Note:
If adding or removing EBP units to the system at the same time, appropriately
adjust battery group number on the system in the UPS (see SmartZone UPS 5-20kVA
User Manual
– Section 2 – Display Operations – Setup Pages – Setup Menu Page –