![Panduit smartzone U01N11L Скачать руководство пользователя страница 75](http://html1.mh-extra.com/html/panduit/smartzone-u01n11l/smartzone-u01n11l_installation-manual_3603814075.webp)
SMARTZONE UPS INSTALLATION MANUAL
74
Figure 88: Disconnect the First Internal Battery Cartridge Connector
d. Slide both battery cartridges out of the UPS.
e. Slide the new battery cartridges into the UPS.
f. Connect the new battery cartridges to the EBP. Press each connector tightly
together to ensure a proper connection.
g. Slide both battery cartridge connectors through the middle hole in the chassis.
h. Replace both battery covers (reverse order of above steps).
i. Replace the EBP faceplate.
j. Turn the breaker on the back of the EBP unit to the ON position.
k. Repeat the above steps for each of the EBP units in the system.
4. After all, EBP battery cartridges in the system have been replaced and are connected
to the system.
5. Change the UPS in the system back to the Normal state.
6. Allow time for the UPS to transitions to the Normal state (about 30 seconds).
7.
Note:
If adding or removing EBP units to the system at the same time, appropriately
adjust battery capacity on the system in the UPS (see SmartZone UPS 1-3kVA User
Manual
– Setup Operation – Double Conversion VRLA UPS – Screen 4) before
running the manual battery test.
8. Manually run a battery test to ensure the battery cartridges is connected.
EBP Battery Cartridge Sets for the 5-10kVA UPS Systems
(UVD240)
Replace battery cartridges with only the same SKU. It is recommended to replace all
battery cartridges in a system at the same time with new battery cartridges of the same
SKU for that unit (EBP).