![Panduit smartzone U01N11L Скачать руководство пользователя страница 78](http://html1.mh-extra.com/html/panduit/smartzone-u01n11l/smartzone-u01n11l_installation-manual_3603814078.webp)
SMARTZONE UPS INSTALLATION MANUAL
77
adjust battery group number on the system in the UPS (see SmartZone UPS 5-20kVA
User Manual
– Section 2 – Display Operations – Setup Pages – Setup Menu Page –
Advanced Setup Menu Page
– Battery Setup Page) before running the manual battery
test.
7. Manually run a battery test to ensure that all battery cartridges are connected.
EBP Battery Cartridge Sets for the 10-20kVA 3-Phase UPS
Systems (UVD480)
Replace battery cartridges with only the same SKU. It is recommended to replace all
battery cartridges in a system at the same time with new battery cartridges of the same
SKU for that unit (EBP).
1. Change the UPS in the system to the Bypass state, this will not allow the UPS to
transition to the Battery state while the battery cartridges are being replaced.
2. Perform the following steps on each EBP unit in the system:
a. Turn OFF breaker on the back of each EBP, this will reduce arching while the
battery connections are being connected and disconnected.
b. Remove the faceplate by pressing both sides of EBP faceplate until the latches
release (see figure below). Then remove the faceplate form the front of the
unit.
Figure 93: Press the Latches to Remove Faceplate
c. Remove and retain the screws (8) and battery baffle from the EBP (see figure
below).